{"id":5233,"date":"2026-01-06T14:28:30","date_gmt":"2026-01-06T13:28:30","guid":{"rendered":"https:\/\/bbtectools.com\/nl\/?post_type=project&#038;p=5233"},"modified":"2026-06-29T09:37:58","modified_gmt":"2026-06-29T07:37:58","slug":"schiphol-bridge-a9","status":"publish","type":"project","link":"https:\/\/bbtectools.com\/en\/projecten\/schipholbrug-a9\/","title":{"rendered":"Schiphol bridge A9"},"content":{"rendered":"<h2 class=\"wp-block-heading\">The Situation<\/h2>\n\n\n\n<p>On behalf of the Rijkswaterstaat (Dutch Department of Public Works), the A9 highway is being expanded. This means that, among other things, the Schiphol bridge must be widened on both sides. To make this possible, the new parts must be anchored to the existing structure by means post-installed rebar with an embedment depths of up to 180 cm with BIS-PE Pure-Epoxy GEN3.<\/p>\n\n\n\n<figure class=\"wp-block-image aligncenter size-full has-custom-border\"><img decoding=\"async\" width=\"712\" height=\"459\" src=\"https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/schipholbrug-1.jpg\" alt=\"\" class=\"wp-image-5817\" style=\"border-top-left-radius:10px;border-top-right-radius:10px;border-bottom-left-radius:10px;border-bottom-right-radius:10px\" srcset=\"https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/schipholbrug-1.jpg 712w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/schipholbrug-1-300x193.jpg 300w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/schipholbrug-1-18x12.jpg 18w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/schipholbrug-1-600x387.jpg 600w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/schipholbrug-1-64x41.jpg 64w\" sizes=\"(max-width: 712px) 100vw, 712px\" \/><\/figure>\n\n\n\n<h2 class=\"wp-block-heading\">The Project<\/h2>\n\n\n\n<p>The&nbsp;<a href=\"https:\/\/bbtectools.com\/en\/c\/drilling\/core-drilling-machines\/\" data-type=\"product_cat\" data-id=\"20\">drilling of the anchor holes<\/a>&nbsp;is a challenging job as the parabolic prestressed reinforcement in the existing bridge section cannot be touched. For this project, Interboor-Midsland, Terra Carta and B+BTec found each other again, after their successful cooperation in&nbsp;<a href=\"https:\/\/bbtectools.com\/en\/our-projects\/schiphol-bridge-a9\/\" data-type=\"project\" data-id=\"5233\">repairing wide slab floors<\/a>.<\/p>\n\n\n\n<p>Terra Carta first mapped the existing reinforcement in great detail using advanced concrete scanning technologies after which a drilling plan for anchoring the new rebar connections could be created.<\/p>\n\n\n\n<p>The drilling of the anchor holes was the next step, for which B+BTec&nbsp;<a href=\"https:\/\/bbtectools.com\/en\/c\/drilling\/core-drilling-machines-and-systems\/drill-stands-drill-accessories\/\" data-type=\"product_cat\" data-id=\"128\">a special drill stand<\/a>&nbsp;designed to allow deep boreholes to be drilled with extreme precision.<\/p>\n\n\n\n<h2 class=\"wp-block-heading\">The result<\/h2>\n\n\n\n<p>Since then, thousands of anchor holes have been drilled passed the existing prestressed reinforcement and just as many rebar dowels have been installed using the new B+BTec injection mortar BIS-PE Pure-Epoxy GEN3 with ETA vlgs. EAD 332402-00-0601 and TR069 for post-installed rebar.<\/p>\n\n\n\n<figure class=\"wp-block-image aligncenter size-large\"><img decoding=\"async\" width=\"1024\" height=\"341\" src=\"https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-1024x341.jpg\" alt=\"\" class=\"wp-image-5869\" srcset=\"https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-1024x341.jpg 1024w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-300x100.jpg 300w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-768x255.jpg 768w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-18x6.jpg 18w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-600x200.jpg 600w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine-64x21.jpg 64w, https:\/\/bbtectools.com\/wp-content\/uploads\/2026\/01\/viaductboormachine.jpg 1500w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>","protected":false},"excerpt":{"rendered":"<p>De situatie In opdracht van Rijkswaterstaat wordt de A9 verbreed. Dit betekent dat onder andere de Schipholbrug aan beide zijden verbreed moet worden. Om dit mogelijk te maken moeten de nieuwe delen aan de bestaande constructie verankerd worden middels stekken die tot een diepte van wel 180 cm verlijmd worden met BIS-PE Pure-Epoxy GEN3. Het [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":5806,"template":"","class_list":["post-5233","project","type-project","status-publish","has-post-thumbnail","hentry"],"blocksy_meta":[],"acf":{"bbtec_project_subtitle":"Speciaalboorstatieven voor diepe precisieboringen","bbtec_project_partners":[5906,5907],"bbtec_project_products":""},"_links":{"self":[{"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/project\/5233","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/project"}],"about":[{"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/types\/project"}],"author":[{"embeddable":true,"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/users\/1"}],"version-history":[{"count":3,"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/project\/5233\/revisions"}],"predecessor-version":[{"id":9720,"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/project\/5233\/revisions\/9720"}],"acf:attachment":[{"embeddable":true,"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/media\/5907"},{"embeddable":true,"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/media\/5906"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/media\/5806"}],"wp:attachment":[{"href":"https:\/\/bbtectools.com\/en\/wp-json\/wp\/v2\/media?parent=5233"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}